Site security planning for NYC and NJ commercial properties: what every system needs
How to plan cameras, access control, intercoms and cabling for a commercial building before anyone prices equipment, worked through one example building from the cellar to the roof.
Technical figures checked against the standards listed at the end.
Swipe the drawing sideways to see the whole building.
Pass 1. Walk the sidewalk, the alley and the roof. Every way in counts, including the doors nobody uses.
- 1Perimeter
- Lobby door, street side
- Shop storefront, the shop's own
- Sidewalk doors into the cellar
- Rear service door to the alley
- Roof door on the stair bulkhead
- Camera views: sidewalk, alley
- 2Entries
- Lobby: call station, reader, strike
- Service door: reader, contact, cameras
- Roof door: contact; lock set by life safety
- Shop back door: who controls it?
- 3Interior paths
- Stair: cellar to roof, floor re-entry
- Elevator: cab reader and camera
- Floors 2 to 6: suite doors, landings
- 4Risers and closets
- Demarc at the front of the cellar
- Riser at the rear, by the stair
- Closet spot by the riser, with power
- Option: second closet on floor 4
A site security plan for a commercial building is a written scope that puts every camera, card reader, lock, intercom station and network closet at a location, with the cable path between them and the rules for who can open which door and when. It comes from walking the building before anyone prices equipment, and it covers six parts: the site walk, cameras and video storage, access control, intercoms, structured cabling, and how the systems work together. This guide works through each part on one example building, with arithmetic you can check.
Buildings in New York City and northern New Jersey add conditions of their own: older construction with few open paths for cable, several tenants behind one street door, cellars that open onto the sidewalk, and closets never meant for network equipment. Most projects still start with a number, such as sixteen cameras and a reader on the front door. That number is a guess until someone has walked the building.
Every figure shows the same building: a six-story pre-war mixed-use building in Brooklyn, 50 ft wide and 100 ft deep. A shop has the ground floor; offices fill floors 2 to 6. People enter through a street lobby door, and deliveries use a rear service door to an alley. One stair runs from the cellar to the roof, and there is one elevator. The carriers bring service into the cellar. It is an example, not a client's building.
01How to start a site security plan: walk the building first
Walk the building in four passes, the same four as Figure 1.
Perimeter
Count every way in from outside, including the ones nobody uses. The example building has five: the lobby door, the shop's storefront, the rear service door, the roof door and the steel sidewalk doors into the cellar. The last two are the ones most often left off a scope, because nobody uses them on an ordinary day.
Entries
For each door, write down its use, who goes through it and when, and what hardware is on it now. The lobby door needs a call station and a reader. The service door is open to deliveries by day and should be locked and watched at night. The roof door is part of the stair, so how it locks depends on the building's fire and life safety requirements; at a minimum it should report when it opens. A shop's back door into the building corridor joins two tenants, and someone has to decide who controls it.
Interior paths
The stair connects every floor, so a locked suite door does little if anyone can climb the stair and walk through an unlocked floor door. The elevator is where most access rules will live: which floors each group of people can reach.
Risers and closets
Find the demarc, where the carriers bring service in; here it is at the front of the cellar. Then find the riser, the vertical path you can actually use between floors; here it is at the rear, beside the stair. Look for a dry spot near the riser with power and room for a wall rack. Those two spots set every cable length, as Figure 6 shows.
The walk produces a written scope: a list and a marked-up plan that put every device and closet at a location, with the cable path between them. If a proposal arrives without one, ask for it before you compare prices. Our article on what a low-voltage scope of work should cover for a NYC commercial security installation goes through it line by line.
02Commercial building security cameras: pixels per foot and storage
Give each camera a job in one line: identify a face at the lobby door, see a person in the alley. The job decides the camera, the lens and the mounting spot, and the count follows from the jobs. Our guide to how many cameras a business actually needs covers common layouts.
The measure that matters is pixel density: horizontal pixels per foot of scene at the person's distance. IEC 62676-4 gives reference densities for four tasks: 250 pixels per meter to identify a person (about 76 per foot), 125 to recognize someone you know (38), 62 to observe what they are doing (19) and 25 to detect that someone is there (8).
Scene width at distance d is 2 × d × tan(half the horizontal field of view); divide the camera's horizontal pixels by it. A 4MP camera is 2560 pixels wide. With an 80 degree lens, the scene 20 ft away is 33.6 ft wide: 76.3 pixels per foot, right at the identify line. At 40 ft the same camera gives 38.1, which only recognizes. A 4K camera with a 100 degree lens gives 40.3 at 40 ft, barely more.
Swipe the drawing sideways to follow the person out the door.
2,560 px ÷ (2 × 10 ft × tan 40°) = 2,560 ÷ 16.8 = 152.5 px/ft
In Figure 2, the narrow lens identifies people all the way out the door, but 10 ft from the camera it sees a strip only 7.3 ft wide, and a person can pass along the wall unseen. The wide lens covers the room but identifies no one past about 14 ft at 4MP. That is why a lobby door usually gets two cameras: one aimed at the door at short range for faces, and one wide view of the room. To try other cameras, lenses and distances, use the full calculator in our article on how far a security camera can see.
These are best cases. Lighting, compression, focus and the angle to the face all cost detail. The usual lobby problem is backlight from a glass street door at midday; a camera with good wide dynamic range helps, and so does a mounting spot that keeps the brightest glass out of frame.
Outside cameras face vibration from trucks and the subway, grime, weather and passersby who can reach a low mount. Mount them out of reach, in housings rated for outdoor use, and plan to clean them. In a landmarked building or historic district, exterior work may still need Landmarks Preservation Commission approval.
No single resolution suits every camera. Choose it per camera from the job and the distance; our security camera installation work starts from that list of jobs.
Size storage from retention, not the other way around
Retention is a policy decision: your own policy, your lease and your insurer set it, and no single number applies to every property. Storage then follows: megabits per second × 86,400 seconds ÷ 8 bits per byte ÷ 1,000 = gigabytes per camera per day. At 4 Mbps that is 43.2 GB. The example building's 14 cameras kept 30 days need 14 × 30 × 43.2 = 18,144 GB, about 18.1 TB before redundancy.
Bitrate is the number to question. It depends on resolution, frame rate, codec and how busy the scene is; a lobby at 9 AM makes far more data than an empty corridor at night. Ask what bitrate an installer assumed. If you record off site, it also sets your upload: 14 cameras at 4 Mbps is a steady 56 Mbps. Our article on how long security camera recordings last goes further into retention.
4 Mbps × 86,400 s ÷ 8 ÷ 1,000 = 43.2 GB
43.2 GB × 14 cameras × 30 days = 18,144 GB
3 drives of 8 TB, raw. Redundancy and the recorder's own reserve add more.
Put the recorder and the PoE switch on a UPS so a short outage does not stop recording, and keep the recorder in a locked closet, not under the front desk.
03Access control for a commercial building: layers, schedules and locks
Access control is a set of rules about who can open which door and when, enforced by readers, locks and a controller and recorded every time. Think in layers: perimeter doors, the core with the elevator and stair, tenant and service spaces, and inner rooms. A person gets a credential only for the layers their work needs.
Figure 4 runs five people through the example building. An office tenant on floor 3 gets the street door at any hour, the elevator to floor 3 and the suite door. The cleaning crew gets the street and service doors, the elevator and the suites from 8 PM to midnight. The shop gets the service door and its own back door. The super gets the building's spaces but not the tenants' suites.
The managing agent grants the street door and elevator. The tenant manages its own suite and staff.
When someone leaves, the credential is removed once and every online reader refuses it from that moment, with no keys to collect. Battery locks not wired to the network update on their next sync, so ask how often that happens.
With several tenants, decide who administers what. The managing agent usually controls the street door, elevator, service door and closets; each tenant may manage its own suite and staff. Set the system up so a tenant's administrator cannot see or change anyone else's people.
The lock on each door
We pick the lock for each door around its use and the building's fire and life safety requirements. An electric strike in the frame releases the latch, and the inside handle keeps working, so people inside can always get out. A magnetic lock on the header holds the door with a magnet and has no handle of its own. A magnetic lock needs a free way out from inside at all times: usually an exit sensor that cuts power as someone walks up, a push button, and release from the fire alarm where the building's requirements call for it. Stair doors and doors on an exit path follow the building's own requirements, which we check on the site visit before any hardware is ordered.
The other early choice is where the system is managed: a cloud service in a browser, or a controller and software on site. Our guide to commercial access control system installation compares cloud management with an on-premise controller, and our access control services page shows how we plan doors.
04Intercom systems for the street door: where each call goes
Without a lobby attendant around the clock, the call station at the street door is how visitors and couriers get in, so plan where each call rings at each hour. In Figure 5, a call rings the front desk by day and the tenant's phone after hours. The person answering sees the visitor and presses unlock; the controller closes a relay, the lock power supply releases the strike, and the system logs who unlocked the door, when, with a snapshot.
Swipe the drawing sideways to follow the signal.
A courier presses the button on the lobby station.
Plan the directory with the tenants: one entry per company or per person, and what happens when nobody answers. Older buildings often have an analog intercom wired to every suite. Sometimes a new panel can reuse that wiring, and sometimes the old cable is too damaged or shared to trust. Test it before assuming either. Our intercom installation page covers video stations and phone apps for multi-tenant buildings.
05Structured cabling for security systems: closets, risers and the 90 m limit
Every device connects back to a closet over structured cabling, and copper Ethernet has a fixed length budget. Under ANSI/TIA-568 the permanent link from patch panel to outlet can be up to 90 m (295 ft), and patch cords add up to 10 m, for a 100 m channel. The limit is the same for Cat5e, Cat6 and Cat6A; a better category does not buy distance.
Figure 6 measures four runs three ways. With the main closet (MDF) at the demarc, every run crosses the cellar to the riser, climbs, and crosses its floor back toward the street; the run to the far front corner of floor 6 comes to about 96 m, over the limit. With the MDF on the riser side of the cellar, that run drops to about 70 m and every run fits. If that spot floods or runs hot, a second closet (IDF) on floor 4, fed by fiber up the riser, brings every upper floor run under 54 m.
Swipe the drawing sideways to see the whole section.
The closet sits where the carriers come in. Every run crosses the cellar to the riser first, and the floor 6 corner run goes over the limit.
Each length is a permanent link: 6 ft at the rack, the path through the riser and ceiling, the drop to the device and 10 ft of service loops, plus 10 percent for routing around beams and ducts. Run C also crosses 30 ft of floor 6 to the far corner, which a section cannot show. All runs use the existing riser at the rear.
Category matters for speed: Cat6 carries 10 Gb/s only to about 55 m, and Cat6A carries it the full 100 m. Cameras and readers need far less, so Cat6 serves them even on the 70 m run. Links between closets and to wireless access points are where Cat6A or fiber pays off. See how Cat5e, Cat6 and Cat6A compare.
The fire rating follows the space. Under the National Electrical Code, Article 800, a ceiling used as an air-handling plenum takes plenum cable (CMP), and a riser takes riser cable (CMR) at a minimum. Many pre-war buildings have both. Every penetration we make through a fire-rated wall or floor is fire-stopped.
Most cameras take power over the same cable (PoE). A switch has a total power budget as well as a per-port limit: up to 15.4 W per port under 802.3af and 30 W under 802.3at. Add the rated draw of every device, including heaters on outdoor cameras, and keep headroom. Readers and locks usually draw from the access controller and a lock power supply, with power coordinated with the electrician.
Whether a permit applies depends on the scope and the building. We check during the site visit and say what applies before work is scheduled. Our structured cabling page covers closets, risers, labeling and testing.
06Integrating cameras, access control and intercoms into one record
Integration means the systems share events, so one thing at a door produces one record. It does not require one manufacturer. It requires an access system, a recorder and call stations that exchange events, which you should confirm in writing before buying.
Figure 7 follows a forced rear service door at 11:42 PM. The door contact reports the door open with no card read and no exit request. The camera above the door bookmarks the clip. The management view shows one entry with the clip attached, and the on-call phone gets the same clip. In the morning nobody has to match a log time to a video timeline.
Swipe the drawing sideways to follow the signal.
Decide who gets notified, and for what. A forced door at night should reach someone; a door held open during noon deliveries should not, or people learn to ignore alerts.
Keep cameras and access equipment on their own network segment, apart from tenant and guest traffic. If you manage several properties, the same events can feed one view across sites; see remote video surveillance for businesses with multiple sites.
07Security system maintenance: what to check and how often
A system nobody checks fails quietly: drives fail, cameras drift or get knocked by a cart, and the credential list fills with people who left. Put these checks on a calendar, and write into the scope who does each one.
- Every camera shows live video and is recording.
- The oldest footage on the recorder matches the retention you set.
- Clean outdoor lenses and housings.
- Test each reader, lock and door contact.
- Check the credential list against current staff and tenants.
- Test the UPS under load.
- Update firmware on cameras, recorder and controllers.
- Review notification rules and who is on call.
The oldest-footage check catches a failed drive before you need the video.
08Questions to ask a security installer before you sign
Bring these to every walk-through and every proposal, including ours.
- Will you give us a written scope that shows every device and its location on a plan?
- For each locked door, how do people get out from inside, and what releases the lock?
- Which camera is meant to identify faces at each entry, and at what distance?
- What retention did you design for, what bitrate did you assume, and how much storage does that need?
- Where will the recorder live, and what keeps it and the PoE switch running in an outage?
- What cable rating will you use above each ceiling and in the riser?
- Which run is the longest, how long is it, and which closet serves it?
- Will every cable be labeled at both ends, with test results handed over?
- Who owns the admin accounts and passwords at handoff, and how are they handed over?
- When a credential is removed, how fast does every door refuse it, including battery locks?
Put the plan in writing
A good plan is short and specific: each device at a location, each door with its rule, each run with its length. Contact Seneca Security to set up a site visit, and we will walk the building with you and write that plan.
09Site security planning FAQ
What should a site security plan for a commercial building include?
It should include a written scope and a marked-up plan that put every camera, reader, lock, intercom station and closet at a location, with the cable path between them. It should also state the access rules for each door and group of people, the video retention and how the storage was sized, and who maintains each part. If a proposal does not show device locations, ask for them before you compare prices.
How many days of security camera footage should a commercial building keep?
There is no single required number. Your own policy, your lease and your insurer set it. Once you pick the number of days, storage follows from arithmetic: at 4 Mbps, one camera records 43.2 GB a day, so 14 cameras kept for 30 days need about 18.1 TB.
What camera resolution do I need to identify faces at a door?
It depends on the distance and the lens as much as the resolution. IEC 62676-4 gives 250 pixels per meter, about 76 pixels per foot, to identify a person. A 4MP camera with an 80 degree lens reaches that out to about 20 ft; farther away, use a narrower lens or a second camera closer to the door.
How long can an Ethernet cable run to a security camera be?
Under ANSI/TIA-568, the permanent link from the patch panel to the outlet can be up to 90 m, plus up to 10 m of patch cords, for a 100 m channel. The limit is the same for Cat5e, Cat6 and Cat6A. A run that would go longer needs a closet closer to the device, or fiber up the riser to a second closet.
Should every access controlled door have a magnetic lock?
No. We pick the lock for each door around its use and the building's fire and life safety requirements. An electric strike in the frame leaves the inside handle working, so people inside can always get out. A magnetic lock needs a free way out from inside at all times.
Do I need a permit to install security cameras or access control?
Whether a permit applies depends on the scope and the building. We check during the site visit and say what applies before work is scheduled. In a landmarked building or historic district, exterior work may still need Landmarks Preservation Commission approval.
Sources and standards
- IEC 62676-4Video surveillance systems for use in security applications, Part 4: Application guidelines. Source of the pixel densities in Figure 2: Identify 250 px/m, Recognize 125, Observe 62, Detect 25.
- ANSI/TIA-568 seriesCommercial building telecommunications cabling. Source of the 90 m permanent link and the 100 m channel in Figure 6.
- TIA TSB-155 and IEEE 802.3an10GBASE-T over Category 6, limited to about 55 m, and over Category 6A to 100 m.
- NFPA 70, National Electrical Code, Article 800Communications cable types, including plenum (CMP) and riser (CMR).
- IEEE 802.3af and 802.3atPower over Ethernet: up to 15.4 W and 30 W per port at the switch.
Have a project in mind?
Send us the address and what you want to cover. We walk the building, then send a written scope. Same-day quotes when we can. Licensed and insured.